Site Name: MIOC Client : Cordant Date of Variation 15-09-17 Site Installation Date: 01-08-17 CONTRACT VARIATION BREAKDOWN SHEET BG Variation Reference...
3 downloads
23 Views
104KB Size
Site Name:
MIOC
Client :
Cordant
Date of Variation Site Installation Date:
15-09-17 01-08-17
CONTRACT VARIATION BREAKDOWN SHEET BG Variation Reference Client Variation Reference Contract drawing reference Drawing revision reference Description of works:
VO1
Wire power supply for condensate pump
SOR Ref
Add/ Omit
Add Add Add Add
Description
Labour Panel materials Installation materials Mileage
Qty
Unit Type
4.0 1.0 1.00 100.00
at at at at
Rate
Amount
£35.00 £65.00 £105.00 £0.50
140.00 65.00 105.00 50.00
Total
360.00
Site Name:
MIOC
Client :
Cordant
Date of Variation Site Installation Date:
15-09-17 01-08-17
CONTRACT VARIATION BREAKDOWN SHEET BG Variation Reference Client Variation Reference Contract drawing reference Drawing revision reference Description of works:
VO2
Wire power supply for sump pump
SOR Ref
Add/ Omit
Add Add Add Add
Description
Labour Panel materials Installation materials Mileage
Qty
Unit Type
4.0 1.0 1.00 100.00
at at at at
Rate
Amount
£35.00 £65.00 £105.00 £0.50
140.00 65.00 105.00 50.00
Total
360.00
Site Name:
MIOC
Client :
Cordant
Date of Variation Site Installation Date:
15-09-17 01-08-17
CONTRACT VARIATION BREAKDOWN SHEET BG Variation Reference Client Variation Reference Contract drawing reference Drawing revision reference Description of works:
VO3
Immersion heaters wiring and control
SOR Ref
Add/ Omit
Add Add Add Add Add
Description
Install Labour Panel materials Installation materials Mileage Commissioning Labour (software mods etc)
Qty
Unit Type
4.0 1.0 1.00 100.00 8.0
at at at at at
Rate
Amount
£35.00 £95.00 £155.00 £0.50 £45.00
140.00 95.00 155.00 50.00 360.00
Total
800.00