Check list for electrical works to be done for building handover:
-
Listed below to be finished before handover:
1. Ground to top floor: 1.1. Power transformer station. / MV lines connected, MV & LV switchgear settings done as designed/ labelled, documented/ clean, locked, IP rating ensured/ ventilation ensured for transformer/ grounding completed/ commercial metering device installed - (check is to performed only if transformer station belongs to client) 1.2. Main switchboard. / Connected, selectivity setting set/ labelled, documented/ clean, locked, IP rating ensured 1.3. Floor distribution switchboards. / Connected, labelled, documented/ clean, locked, IP rating ensured 1.4. Emergency lights indoor / automatic switch on and duration test 1.5. External emergency lights 1.6. Lights in the lobby on the ground floor. Control panel for the lobby lights. Scenario programming. 1.7. Lights in BOH rooms, corridors, WC and in the lobby on the ground floor. Switches, movement sensors. 1.8. Lights in BOH rooms in floors 1 to 5th, switches. 1.9. Lights in corridors, movement sensors. 1.10. Lights in staircases, movement sensors. 1.11. Light control panel in reception. To be programmed by SHM spec. 1.12. Outdoor lights 1.13. Sockets ground floor, corridors on floors, BOH rooms. 1.14. Floor boxes ground floor lobby. 1.15. Floor boxes with electrical and data sockets, HDMI cable for the meeting room – general installation and coordination with the furniture. 1.16. Data sockets for TV wall, reception, bar, WiFi AP, CCTV-IP on the ground floor – to be connected, labelled. 1.17. Data cable connection, labelling and testing ground floor and 1-6 floors - to be labelled. 1.18. Data cabling tests to be done. 1.19. SOS call system public toilets, deluxe rooms. 1.20. Sound system for the ground floor: cables, loudspreakers in ground floor and in elevators, control panels in reception. 1.21. Power connection for data racks on floors. 1.22. CCTV cameras inside, outside.
1.23. 1.24.
Access control for external door. Card operated locks for BOH doors.
1.25.
Intercomm system.
1.26.
UPS for reception and for bar sockets.
1.27. 1.28. 1.29.
Fancoil‘s control for lobby. BMS panel, BMS system. Fire alarm system.
2. On the Roof: 2.1. Installation of the lightning system on the roof to be finished 2.2. Grounding system, downconductors – installation, measurements, labeling. 2.3. AHU wiring and installation 2.4. Cable and downconductor wires penetration through the roof. 2.5. Roof antenna cables
3. In rooms: 3.1. All the power sockets tested guestrooms. 3.2. All the lights functionally tested in guestrooms. 3.3. Thermostats programmed. 3.4. Installation of missing sockets, switches, blind covers in deluxe room and for TV in standard rooms . 3.5. Thermostat & water sensor installation for deluxe rooms. 3.6. Fancoil installation, connection and testing for deluxe rooms. - To be presented before handover: 4. As built documentation 4.1. Drawings, schemes, data sheets, test protocols provided for electrical installations. 4.2. Maintenance and operational instructions to be presented. - To be provided before opening: 5. Operational instructions to be presented and training to be provided for Operator for the following systems: Fire alarm, Lights control, Sound system, Fancoils public area control, SOS call system, Rotating door, Intercom, Access control, BMS panel, BMS panel alarms.